Project Manager: Henry Smith
Take the surveyThis project will replace the restroom at this park, and will consider adding a new community events space.
Project Overview
This project proposes to construct a permanent combined restroom and pumphouse building in Jefferson Park, replacing the portable restrooms currently in use. This building will serve as a long-term replacement for the restroom building that was damaged by fires in 2021. Additionally, this project will consider the expansion of the building footprint to include a small community space designed to support events and activities within the park.
Design mockups will be available and shared here in early 2026.
Project Timeline
- Winter 2026: Community outreach and engagement
- Online design survey open Feb. 18-March 9, 2026
- 2026 – Design
- 2027 – Construction