Project Manager: Kristi Evans
This Central Tacoma facility has a new schematic plan rooted in community priorities, which includes an all-season, multi-sport field.
Latest Updates
February 2026
Parks Tacoma is currently in design for Phase 2 for Peck Community Sports Park. Construction is anticipated to begin in summer or fall 2026.
On August 11, 2025, the Park Board approved a $703,232 contract with Fora Landscape Architects to provide design support through construction of Phase 2 of the project. This will include:
- Full design development for the entire park, informed by additional community input, and
- Construction documents, permitting and construction-phase services for a synthetic multi-use sports field, fencing, and restroom building.
Peck Community Sports Park Projects
Parks Tacoma comprehensively and collaboratively developed a schematic plan for Peck Community Sports Park (formerly known as Peck Athletic Complex) that reflects the community’s priorities, along with the placement of one all-season, multi-sport field at this location. The Park Board approved the updated master plan on December 11, 2023.
To our community members who engaged in this redesign process with us, thank you. Your input and conversation directly informed the updated master plan that reflects the community’s priorities.
- Phase 1 focused on the construction of Tacoma Public School’s baseball field, which was complete in December 2024.
- Phase 2 includes the design and construction of a multiuse synthetic field, fencing and restroom.
News
Inspiring the next phase of design for Peck Community Sports Park
Plan to build second field and restroom building at Peck Community Sports Park moving forward
Tacoma Public Schools and Parks Tacoma celebrate grand opening of Aaron Pointer Field—Home of the Stadium Tigers
Timeline
Community Engagement & Outreach: Spring-Fall 2023
Phase 1: Tacoma Public School’s baseball field construction
- Construction complete: December 2024
- Ribbon-Cutting Ceremony: January 15, 2025
Phase 2: Multiuse Synthetic Field Design Construction
- Design & construction: 2025-2027
- Anticipated to accommodate baseball, soccer, t-ball, kickball, & more
- August 11, 2025: Park Board Meeting
- The Park Board approved a resolution for contract with Fora Landscape Architects to complete Phase 2, consisting of:
- Full design development for the entire park, informed by additional community input, and
- Construction documents, permitting and construction-phase services for a synthetic multi-use sports field, fencing, restroom building.
- The Park Board approved a resolution for contract with Fora Landscape Architects to complete Phase 2, consisting of:
- Public meeting: September 25, 2025, 6:00-7:30 pm. Learn more.
- Construction start: Summer-Fall 2026
- Anticipated completion: Spring 2027